SCI Bridge: Brunswick Bridge 40
Project: Brunswick Bridge 40, Brunswick County, NC
Division: Bridge and Heavy Construction
Service Period: May 2023 – November 2023
Scope: The bridge on State Route 1515 over Mill Creek in Brunswick County needed to be replaced due to structural deficiency, as it had reached the end of its design service life. NCDOT awarded the bid for construction of a new bridge to SCI.
Services: Within a tight timeframe of six months, SCI demolished the original structure, completed the new two-span structure and approach work, and paved the bridge and added markings to complete the project.
Success: SCI was able to complete this project and open the road to traffic in late November 2023, ahead of the original schedule set by NCDOT.