SCI Site Development: Morganton Park South

Airel view of Morganton Park.

Project: Carolina Green Parkway & Morganton Park South Phase 1, Southern Pines, NC

Division: Site Development

Service Period: October 2022 – July 2024

Scope: Midland Atlantic and Ashland Construction contracted SCI to provide site development services for the Carolina Green Parkway and Morganton Park South retail project in Southern Pines, NC.

Services: SCI delivered a turn-key scope of work for the parkway and retail space simultaneously. The project took nearly two years to complete, spanned a combined 50 acres of land, and provided aesthetic enhancements and infrastructure improvements to the corridor and development.

Challenges: The relocation of conflicting dry utilities caused work delays in critical areas, and 600,000 cubic yards of dirt needed to be moved between project sites.

Rewards: With proactive planning and hard work, SCI was able to move the dirt between the two sites, eliminating the need to export access material, and successfully meet all completion deadlines.